Project Timeline

Welcome to the official progress page for Masjid Madinat Al Zahra.

​

Every stage of this journey — from foundation to final touches — reflects the dedication, unity, and support of our community. With your duas and contributions, we move closer each day to completing a place of worship that will serve generations to come, inshaAllah.

 

May Allah accept this effort and reward all those involved — Ameen.

Madinat Al Zahra’s Golden Dome Shines Bright

On September 30, 2025, Madinat Al Zahra Masjid reached a significant milestone with the installation of its new golden dome — a symbol of unity, faith, and the timeless beauty of Islamic architecture. A small ceremony was held to mark the occasion, attended by members of our community who gathered to witness this inspiring moment.​

​

Experience the joy of this historic occasion by clicking here and watching the video.

Key Stages in the Masjid Development

  • February 2017
    Workshop event at Café Zoya held for key post holders of MQI.

  • February 2017
    Approval of planning conditions received. Demolition work began, and conversion of the temporary building commenced.

  • November 2016
    Submission of pre-commencement planning condition documents.

  • June 2016
    Official planning decision and approval received.

  • April 2016
    Planning and Appeals Committee hearing held.

  • November 2015
    Full Planning Application (15/06524/MAF) and Listed Building Consent (16/01881/LBC) submitted.

  • May 2015
    Fundraising event held at Café Zoya. A project presentation was delivered to members of MQI.

  • April 2015
    Meeting held with Michael Eaglestone to discuss the submitted design.

  • March 2015
    Second consultation held. Further information shared as part of a developed design phase. Main issue raised concerned the demolition of a listed building.

  • August 2014
    Further information received from the planning department highlighting key aspects of the development needing focus and attention.

  • Jun / Jul 2013
    Design team appointed to undertake design work required for planning approval.

  • March 2013
    Community event at Rio Grande. An initial feasibility study document was presented.

  • Oct / Nov 2012
    Initial site discussions and exploration of potential. Several meetings held over a 3–4 month period to begin the purchase process.