Project Timeline

Welcome to the official progress page for Masjid Madinat Al Zahra.

Every stage of this journey — from foundation to final touches — reflects the dedication, unity, and support of our community. With your duas and contributions, we move closer each day to completing a place of worship that will serve generations to come, inshaAllah.

 

May Allah accept this effort and reward all those involved — Ameen.

Madinat Al Zahra’s Golden Dome Shines Bright

On September 30, 2025, Madinat Al Zahra Masjid reached a significant milestone with the installation of its new golden dome — a symbol of unity, faith, and the timeless beauty of Islamic architecture. A small ceremony was held to mark the occasion, attended by members of our community who gathered to witness this inspiring moment.

Experience the joy of this historic occasion by clicking here and watching the video.

Key Stages in the Masjid Development

  • February 2017
    Workshop event at Café Zoya held for key post holders of MQI.

  • February 2017
    Approval of planning conditions received. Demolition work began, and conversion of the temporary building commenced.

  • November 2016
    Submission of pre-commencement planning condition documents.

  • June 2016
    Official planning decision and approval received.

  • April 2016
    Planning and Appeals Committee hearing held.

  • November 2015
    Full Planning Application (15/06524/MAF) and Listed Building Consent (16/01881/LBC) submitted.

  • May 2015
    Fundraising event held at Café Zoya. A project presentation was delivered to members of MQI.

  • April 2015
    Meeting held with Michael Eaglestone to discuss the submitted design.

  • March 2015
    Second consultation held. Further information shared as part of a developed design phase. Main issue raised concerned the demolition of a listed building.

  • August 2014
    Further information received from the planning department highlighting key aspects of the development needing focus and attention.

  • Jun / Jul 2013
    Design team appointed to undertake design work required for planning approval.

  • March 2013
    Community event at Rio Grande. An initial feasibility study document was presented.

  • Oct / Nov 2012
    Initial site discussions and exploration of potential. Several meetings held over a 3–4 month period to begin the purchase process.